avatar Yosemite National Park Continues Work on Pavement Preservation Project
July 07, 2011 12:41PM
Yosemite National Park Continues Work on Pavement Preservation Project
July 6 Update (expect up to 15-minute delays)

El Portal Road
This week, July 5th thru the 8th crews will be working nights crack sealing from 9:00 PM to 7:00 AM. Next week, July 11th and 12th crews will be working during the day microsealing turnouts from 6:00 AM to 5:00 PM. Please anticipate closure of turnouts along the El Portal Road next Monday and Tuesday, then as soon as the material has cured, the turnouts will be reopened to traffic.

Rancheria and Old El Portal Areas
For this week and next (July 5th thru July 8th, Monday thru Friday), crews will continue with crack sealing and pothole repairs throughout the community from 7:00 AM to 5:00 PM. Next week, July 11th thru 15th crews will be microsealing various roads in Rancheria and Old El Portal from 7:00 AM to 5:00 PM. For each work area, crews will be installing signs to notify residents when work is occurring on a particular street or parking area, so please move your vehicles when crews are working in your area. Next week is the beginning of the final surface treatment, so some of the narrow roads will require closure for up to 4-hours as the material cures, while others may require detours. Also, unless it is an emergency, please do not drive on the new pavement until you are directed to do so.

Crane Flat Campground
Crews will be chipsealing the main entrance road on Thursday, July 7th.

Foresta Road East (Foresta Community)
Crews will be chipsealing the Foresta Road on July 18th, between the Big Oak Flat Road and the Dumpster Area.

Hodgdon Area
Crews will be completing pothole repairs July 12th and 13th, then chipsealing the various roads July 14th and 15th, so please follow the guidance of the traffic control staff to avoid getting oil on your vehicles.

El Portal Administrative Parking Complex
Crews are planning to complete pothole repairs on July 8th and 11th, then crack sealing on July 10th (Sunday, to minimize impacts to park operations). Please advise your staff they can move the government vehicles to concrete areas, because we are only crack sealing and patching the asphalt surfaces.
avatar Re: Yosemite National Park Continues Work on Pavement Preservation Project
July 26, 2011 06:53AM
Yosemite National Park Continues Work on Pavement Preservation Project
El Portal Road - Crews will be cleaning along the El Portal Road next week (July 25th thru 29th) with minimal delays 7:00 AM to 5:00 PM. Tentatively, on August 31st, crews will be working nights (9:00 PM to
7:00 AM) placing a surface treatment on the El Portal Road between the Big Oak Flat Intersection and Parkline (Yosemite View Hotel), expect up to 15-minute delays. There will a large number of trucks for this surface treatment, so please be cautious and aware when going thru the construction zone.
Rancheria and Old El Portal Areas
Rancheria - Next week July 25th, crews will be removing the excess rocks off the chipseal area in Rancheria. Then on Tuesday, July 26th crews will be fog sealing the same chipseal area. For each work area, crews will be installing signs to notify residents when work is occurring on a particular street or parking area, so please move your vehicles when crews are working in your area. Please follow the direction of the traffic control staff to guide you thru the work zones.
El Portal Administrative Parking Complex - Crews are planning to microseal the first lift of all the paved asphalt surfaces July 23rd (Saturday) and 24th (Sunday) and the 2nd lift of microseal on the July 30th and 31st. Please advise your staff they can move the government vehicles to concrete areas, because we are only crack sealing and patching the asphalt surfaces. Expect delays if you are entering this area over the next couple of weekends.
Crane Flat Campground - Crews will be fog sealing on Friday July 26th thru the 28th, with traffic control from 7:00 AM to 5:00 PM. Expect delays and please follow the guidance of the traffic control staff.
Foresta Road East (Foresta Community) - Crews will be placing a fogseal July 27th with traffic control 7:00 AM to 5:00 PM, between the Big Oak Flat Road and the Dumpster Area. Expect delays and please follow the guidance of the traffic control staff.
Hodgdon Area - On July 29th crews will be placing a fog seal over the chipseal areas with traffic control 7:00 AM to 5:00 PM. Expect delays and please follow the guidance of the traffic control staff.



The cure for a fallacious argument is a better argument, not the suppression of ideas.