BLM Lifts Suspension of Activities Order for Ivanpah Solar Electric Generating System

All posts are those of the individual authors and the owner of this site does not endorse them. Content should be considered opinion and not fact until verified independently.

avatar BLM Lifts Suspension of Activities Order for Ivanpah Solar Electric Generating System
June 10, 2011 03:36PM
The Bureau of Land Management has issued a notice today allowing construction to resume on parts of the Ivanpah Solar Electric Generating System. An immediate temporary suspension of activities decision was issued April 15 and has now been lifted since the U.S. Fish and Wildlife Service issued a new Biological Opinion concluding the project will not jeopardize the threatened desert tortoise.

The BLM reinitiated consultation with the FWS in March after the project proponent BrightSource Energy reported finding more tortoise in the project area than originally anticipated. The BLM issued an Immediate Temporary Suspension of Activities decision for the project in April when project biologists reported reaching the limit of number of tortoises handled under the original Biological Opinion.

After reviewing the new information and clearance data at the project site, the FWS issued a new Biological Opinion today that includes new stipulations for translocating tortoise as well as new requirements for protecting them from predators and increased monitoring and fencing.

“This new Biological Opinion allows the project to move forward without jeopardizing the tortoise, taking into account the higher number of animals found,” said BLM-California Acting State Director Peter Ditton. “We worked closely with the Fish and Wildlife Service throughout the development of this new BO and will continue to work together to monitor construction of the ISEGS project.”

The BLM issued a Notice to Resume Activities and Notice to Proceed on Units 2 and 3 today, giving BrightSource the green light to resume construction with the new stipulations and requirements for protecting tortoise. Approved construction will include the power block in Unit 2 and the Unit 3 access road. Work on the heliostat fields in Units 2 and 3 will not move forward until the tortoise translocation window reopens in the fall when the weather cools. The new Biological Opinion and Notice have been posted on the BLM website at http://blm.gov/b45c.