avatar Tioga Road
April 15, 2004 11:59AM
<HTML>Plowing of Tioga Road starts today.</HTML>

avatar Re: Tioga Road
April 19, 2004 06:00PM
<HTML>Tioga Road Progress Report

Friday, April 16

Starting Location: 11 miles from Crane Flat; Ending Location: 14 miles from Crane Flat (at White Wolf)

Total distance plowed: 4 miles; Average snow depth: 3 1/2 feet



Saturday, April 17

Starting Location: 14 miles from Crane Flat; Ending Location: 19.8 miles from Crane Flat (Yose Creek Grade)

Total distance plowed: 5.6 miles; Average snow depth: 3 1/2 feet</HTML>

avatar Re: Tioga Road Snow Plowing Report
April 20, 2004 10:26AM
<HTML>Starting Location - 20 miles from Crane Flat Gate

Ending Location - 24 miles from Crane Flat Gate

Distance Plowed - 4 miles

Average snow depth is 3 feet.</HTML>

avatar Re: Tioga Road Snow Plowing Report
April 22, 2004 12:34PM
<HTML>Progress report for Tioga Road April 21, 2004



Starting Location 24 miles from Crane Flat Gate

Ending Location 28.4 miles from Crane Flat Gate, at Olmstead Point

Average snow depth is 3 feet

April 22, we will be plowing through the Olmstead Avalanche zone.



The East Side (Mono County) has started to plow into the Park from the Tioga Gate. Their progress for today was one mile. They are in to very dense and deep snow. Average depth is 5 feet with drifts of up to 8 feet.</HTML>

avatar Re: Tioga Road Snow Plowing Report
April 27, 2004 11:58AM
<HTML>Tioga Road has been plowed through. Work remains to be done to make the road safe for travel and no opening date has been set.</HTML>