Valley Pavement Preservation Project Schedule Update

All posts are those of the individual authors and the owner of this site does not endorse them. Content should be considered opinion and not fact until verified independently.

avatar Valley Pavement Preservation Project Schedule Update
October 09, 2015 09:59AM
The following is the updated schedule for the Valley Pavement Preservation Project which will continue until mid November, 2015.

Typical work week will be Monday thru Friday from 8:00 AM to 5:00 PM. Please allow time for delays when traveling thru the various construction zones and expect up to 15 -minute delays and some detours around work zones.
  • 10/8 El Capitan Crossover, Southside Drive
  • 10/9 Southside & Northside Drive and the Valley School Parking Area(After 2PM)
  • 10/12 Mirror Lake Road
  • 10/13 Curry Village Drive, Village Drive, & Village Store (North Lot)
  • 10/14 Curry Village Drive, Village Drive & Village Store (South Lot) & West Valley Residence Area
  • 10/15 Ahwahnee Drive (50%), Yosemite Lodge Parking Areas (Buildings 4200 to 4500), Yosemite Lodge Road (15%), El Capitan Picnic Area Parking,
  • 10/16 Ahwahnee Drive (50%), Yosemite Lodge Parking Areas (Buildings 4100), Yosemite Lodge Road (15%), Bridalveil Falls Parking Area
  • 10/19 Yosemite Lodge Parking Areas (Cedar Building 3900), Yosemite Lodge Road (15%)
  • 10/20 Yosemite Lodge Parking Area (Buildings 3500-3600), Yosemite Lodge Road (15%)
  • 10/21 Yosemite Lodge Registration Area, Yosemite Lodge Road (15%)
  • 10/22 Yosemite Lodge Parking Areas (Buildings 3200 to 3400), Yosemite Lodge Road (15%)
  • 11/9 Upper Pines Campground
  • 11/10 Lower Pines Campground
  • 11/12 North Pines Campground
  • 11/6-20 Striping at various Valley Locations