Around South Entrance: There will be 30-minute delays (Mon.-Fri.) with single lane traffic control 6AM to 6PM as crews continue finalizing the remaining road punch list items (striping, smoothness grinding, cleanup, etc.) around the South Entrance Intersection. Weather permitting the delays will continue through January 19th. The crews will also be working this coming Saturday with 15-minute delays in an effort to complete the remaining weather dependent Wawona Road work before the expected cold weather next week.
Between the Rostrum and the Wawona Tunnel: There will be up to 15-minute delays 6AM to 6PM on Thursday and Friday this week (1/11 & 12/18) as crews complete placing the final pavement markings along this area of the Wawona Road.