<HTML>The annual pavement striping is tentatively scheduled to start Mon., March 24. Most of the work will occur between 8:00 pm and 6:00 am. The projected schedule is to start with the El Portal Road and the Valley floor. This will probably take three to four days to accomplish. From there, the contractor will be going to the Wawona Road, then the Big Oak Flat Road. All stencil painting will also start on Monday. This will be a nightly operation also and will probably take four weeks to complete. All of this work is dependant on weather conditions and nighttime temperatures.</HTML>