Reconstruct El Portal Road at the "Narrows" (a 1/4 mile section of road upstream of the Big Oak Flat Road (with connections to Highway 120)/El Portal Road intersection)

Please note the following update on the contractor's construction schedule for the El Portal Road reconstruction at the "narrows":

The following traffic impacts will last through noon May 23, after which the road will be open to 2-way traffic:

Monday through Saturday – 30 minute delays from 6:00 a.m. until 10:00 p.m.

Night closures will occur on Sunday through Thursday nights from 10:00 p.m. until 6:00 a.m. with an opening at 11:00 p.m. for shift workers.

There will be night work after the Memorial Day Holiday from 10:00 PM to 6:00 AM but it will NOT result in road closure. Traffic control will be coordinated with the Valley Loop Road project in that the same pilot vehicle will take motorists through both projects (between El Capitan Crossover and BOF intersection). We expect the delay to be 30 minutes. This will begin on Tuesday 5/27 and may continue 7 days a week.

Call 372-0200.1.1.2 for last minute updates on the status of the opening/closure of this road.

avatar Re: Construction at the "Narrows"
June 03, 2008 10:34AM
There will be construction activity causing delays nightly except Sundays through 6/14:

Mon – Thurs – 8:00 p.m. – 6:00 a.m. Traffic control will be coordinated with the Valley Loop Road project.

Fri – Sat - 10:00 p.m. – 6:00 a.m.

The guardwall will be complete except for stain on May 30.

The curb and drop inlets will be complete on May 29.

Final paving is scheduled for 6/4 & 5, with striping and raising manholes on 6/6 & 7.

Completion of the cut wall facing is scheduled for 6/14.

Guardwall staining is scheduled for 6/12 - 14.

Final inspection is scheduled for 6/10 at 11:00 a.m.