Re: Arch Rock Construction

All posts are those of the individual authors and the owner of this site does not endorse them. Content should be considered opinion and not fact until verified independently.

avatar Arch Rock Construction
March 01, 2010 05:30PM
How is the construction going on? They should be near completion. I spent a lot of time in that old booth.
avatar Re: Arch Rock Construction
March 01, 2010 08:37PM
u talking about hwy 140 entrance?
avatar Re: Arch Rock Construction
March 01, 2010 10:11PM
Yes. They're getting a new booth. Hopefully the air conditioning will work better than the old one. That's the hottest spot in the park. It gets over 110 degrees in that booth during the summer.
avatar Re: Arch Rock Construction
March 02, 2010 01:59PM
Quote
Dave
It gets over 110 degrees in that booth during the summer.

That'd explain the cranky rangers. winking smiley



Edited 1 time(s). Last edit at 03/02/2010 02:44PM by eeek.
avatar Re: Arch Rock Construction
March 02, 2010 02:38PM
Quote
eeek
Quote
Dave
It gets over 110 degrees in that booth during the summer.

That'd explain the crank rangers. winking smiley
No, there's other explanations for that. They try their best to be professional. If only the visitors would do the same.
Re: Arch Rock Construction
March 02, 2010 04:10PM
In my experience, the rangers have been uniformly professional, in spite of the wretched behavior of some visitors.
Taking pizza bribes, however...
avatar Re: Arch Rock Construction
March 02, 2010 04:20PM
Quote
wagga
In my experience, the rangers have been uniformly professional, in spite of the wretched behavior of some visitors.

My comment was meant as humor.

Quote

Taking pizza bribes, however...

They don't do that when the booth is at 110 F. Ice cream maybe...
avatar Re: Arch Rock Construction
March 02, 2010 05:01PM
Quote
eeek
Quote

...Taking pizza bribes, however...

They don't do that when the booth is at 110 F. Ice cream maybe...

That's been done, and greatly appreciated.
avatar Re: Arch Rock Construction
March 02, 2010 04:58PM
Quote
wagga
In my experience, the rangers have been uniformly professional, in spite of the wretched behavior of some visitors.
Taking pizza bribes, however...
You can't feed the bears.... but you can feed the rangers.Feed ME!

They do try hard. Most love the job and don't mind the heat or the occasional difficult visitor. I was able to disarm a few and had them smiling when they left.
avatar Re: Arch Rock Construction
March 02, 2010 03:02PM
when i went through there about 3 weeks ago, it was way far from being completed! in fact, the early afternoon i went there (on a weekday)., no work was being done.
avatar Re: Arch Rock Construction
March 02, 2010 04:56PM
Quote
forrestranger
when i went through there about 3 weeks ago, it was way far from being completed! in fact, the early afternoon i went there (on a weekday)., no work was being done.
They're probably waiting for a busy weekend to continue the work. cool smiley
avatar Re: Arch Rock Construction
March 02, 2010 08:28PM
Quote
Dave
They're probably waiting for a busy weekend to continue the work. cool smiley

lolol probably right... i remember the day i went, i was wondering why no one was working.. there was a light drizzle of rain, but not for very long.