The contractor will be grinding bumps on the new pavement at 3 locations between Ellery Lake & Blue Slide, and removing the remaining signs, equipment, etc. on Wednesday, 7/28/10, using traffic control with flaggers from Tioga Pass Park Entrance to 5.5 miles east. Delays are not to exceed 20 minutes. It is anticipated this work will be done in the morning, after which, all work for the paving project will be complete.
Guardrail work will resume today, Monday 7/26/10 starting at Warren Creek & continue east. This work is expected to be completed by Fri 7/30/10 and may cause minimal delays.